Substation improvements

  • Oil testing and dissolved gas analysis completed on 23 substation transformers and 81 substation regulators.
  • Bi-Annual substation infrared inspections were completed to look for equipment and hardware loose connections.
  • Maintenance change-out of 15 substation voltage regulators and 7 substation reclosers over the past year.
  • Completed inspections of field equipment on the distribution lines, which consists of 32 voltage regulators, 46 capacitor banks and 38 reclosers.

Construction highlights

  • 12,908 poles inspected and tested
  • 509 (3.9%) poles identified for replacement
  • 23,381 meter locations inspected and readings verified
  • 53.1 miles of overhead / underground wire and cable added or replaced