November Rights-of-Way Maintenance Schedule - Carolina Country
November 2021

During November, Lucas Tree will be trimming out our Rose Bay circuit along Highway 264 and adjoining roads.

Gunnison Tree will be trimming out the Hyde County circuit that originates at our Pantego substation and ends just west of Bible Shore Road.

Lee Construction crews will be working on Allen Road on the Dowry Creek circuit. A second crew will be working on the Rose Bay circuit along Highway 264. And a third crew continues to work on the Merritt circuit along Orchard Creek Road.

River City Construction continues the ductile pole conversion project between our Five Points and Washington substations.

Osmose crews are continuing pole inspections and will be working on the Rose Bay circuit during November. Please give our crews and contractors wide berth if you should encounter them along roadways.