April 2023

Tideland has hired Lucas Tree Experts to manage vegetation in our rights-of-way.

During April, Lucas will work on all three Ocracoke village circuits. A second crew will also work on the Bonnerton circuit out of our Edward substation before moving onto the Lowland circuit.

Lee Electric line construction crews will work on the Rose Bay circuit out of Ponzer substation and the Merritt circuit out of our Silver Hill substation.

Metered service safety inspections will wrap up in Ocracoke before moving on to our Engelhard operational district in mainland Hyde County.

Thank you for your support of each of these important maintenance activities, which improve system reliability and promote public safety.

Be sure to give all utility crews wide berth when approaching them on public roadways.

Reminder

Always call 8-1-1 before you start any construction or excavation project to have all utility lines properly identified and marked.