June rights-of-way maintenance schedule - Carolina Country
June 2023

Tideland has hired Lucas Tree Experts to manage vegetation in our rights-of-way.

During June, Lucas will be trimming along the Lowland circuit out of our Edward substation.

Lee Electrical Construction crews were scheduled to finish the Rose Bay project in May. They will next move onto the Swan Quarter circuit including downtown Swan Quarter.

River City Construction is working along Hwy 33 on the Blounts Creek circuit.

Osmose will be conducting pole inspections on the circuits originating out of our Plymouth and Five Points substations. Keep in mind that these inspections often include a hammer test to determine pole integrity along with digging at the base of the pole.

Metered service safety inspections are wrapping up in Engelhard operational district in mainland Hyde and Dare counties.

Thank you for your support of each of these important maintenance activities which improve system reliability and promote public safety.

Be sure to give all utility crews wide berth when approaching them on public roadways.

Reminder

Always call 8-1-1 before you start any construction or excavation project to have all utility lines properly identified and marked.

nc811.org

Like this?

Share it with others