Tideland EMC

October rights-of-way maintenance schedule

Tideland has hired Gunnison Tree Service to trim trees in our rights-of-way.

During October, Gunnison will be trimming the following circuits in Hyde County: Fairfield, Prison, Mattamuskeet substation and Lake Comfort.

Contract construction crews with Lee Electrical will be working north of the Pamlico River to
continue proactive pole replacements at locations identified by our Osmose inspectors.

Reminder

Always call 8-1-1 before you start any construction or excavation project to have all utility lines properly identified and marked.