New overhead lines restored transmission service to the islands. (Photo by CHEC).
“This was an unprecedented event. We’re so grateful to cooperative and contract crews for their tireless efforts to restore power, and to cooperative members and visitors of Hatteras and Ocracoke Islands for their continued patience and support,” CHEC General Manager Susan Flythe said. “North Carolina Electric Membership Corporation, NCDOT, and county and state officials also provided continued support and resources during restoration efforts.”
Electric co-ops across the state provided supplies, and Brunswick Electric and Roanoke Electric Cooperative provided crews for support throughout the restoration process.
After assessing the damage, CHEC and a team of contractors and specialists began two simultaneous projects to restore power from the mainland: repair of the underground cables and construction of a new overhead line.
“I told people, don’t cancel your vacations, because they’re going to work hard,” Governor Roy Cooper said following a visit to the site. “They’re going to work hard to get this thing fixed.”
PCL Construction was able to reveal all three cables, one of which was successfully spliced and repaired, but water continued to seep into the excavated trench, making it unsuitable for full repairs. The overhead option was deemed the safest, quickest way to restore power (see map above).
“Ahead of storms, we’re able to have some sense of coming outage issues, but this was one of those instances that comes out of the blue,” said Tideland EMC General Manager and CEO Paul Spruill. “We’re very appreciative of our members, who took early calls for conservation seriously. Some of our largest island members agreed to remain on their own standby generation while we normalized loads on diesel generators. Managing this was really a community effort.”