Crews transfer the cable to the modified “beach” vehicle. Daniel Pullen photos
The new cable is represented in red in the image above. Tideland EMC operations department graphic
Nearly 100 tons of submarine power cable arrived at the south end of Hatteras Island on January 17. It officially marked the operational start of Tideland’s project to counteract rapid coastal erosion and ensure reliabile transmission service to Ocracoke.
The long awaited start of Tideland’s Hatteras Island submarine cable project finally kicked off with the arrival of the cable itself. It was quite a journey to get there.
The cable arrived by barge in Virginia where it was then transferred to a transport vehicle. Interestingly, the oversized load was only authorized to travel on Virginia roads after dark. In North Carolina, travel was restricted to daylight hours. The transport team camped out at the border overnight to comply with each state’s travel permit.
Trenching and dewatering work underway. Ben Beagle photo
Two cranes offloaded the cable from the transport vehicle and onto a modified “beach” truck that will move the cable along Pole Road during the burying process. A system of wooden mats, similar to those used in logging operations, is used to keep the truck moving along the sandy stretch of road.
By the first week of February, just over 500 feet of cable had been installed. When complete, 10,800 feet will have been installed to connect with the existing 20,450 feet of submarine cable that crosses Hatteras Inlet to provide electric service to Ocracoke.
Depending on weather, the project should be complete by April.