Tideland has hired Lucas Tree Experts and Gunnison Tree to trim trees in our right-of-way. During December, Lucas will be trimming the Craven County circuit out of our Edward substation. This includes the Tunstall Swamp area and all side roads. Gunnison will be trimming the Pungo circuit along Highway 99.
Lee Electrical construction contractors will be doing overhead line work on the Maribel Tap off the Merritt circuit.
We appreciate your support of these important maintenance operations which improve system reliability.
Reminder
Always call 8-1-1 before you start any construction or excavation project to have all utility lines properly identified and marked.